In accordance with Section 104.7.2 of the International Fire Code, South Davis Metro will require a “technical opinion and report” (peer review) of all plans for the installation and/or modification of an automatic fire protection system, installation and/or modification of fire alarm and detection systems and related equipment, fire pumps and related fuel tanks, jockey pumps, controllers and related equipment, installation, modification, or removal from service of a standpipe system.  Click here for more information.

  • SITE PLAN REVIEWS - reviews are $100 and need to be paid prior to the review. If the review takes longer than one hour, you will be notified what the additional fee is, the additional fee will need to be paid then your review will be sent out via email.

  • DEFERRED SUBMITTALS - will require a plan review fee of $100 if there are less than 10 devices. If there are more than 10 devices, the plans will need to be reviewed by a qualified 3rd party reviewer (Click here for 3rd party review info.) and will not require a plan review fee. All projects will require an installation permit; Fire Sprinkler permits are $300 and include 3 inspections; Fire Alarm permits are $200 and include 2 inspections. Please refer to the SDMF Permit Fee Schedule for more information. 

  • Step 1 – Submit Online Application & Pay Fees:
    Please fill out online form below and pay fees. Fees must be paid before your plan review can begin.

               ~Plan Review Application

               ~Pay Fees here

    Step 2 – Submit Plans:
    Submit plans to fireplans@sdmetrofire.gov

    Step 3 – Plan Review & Project Clearance Letter:
    After steps 1 and 2 are completed, the Fire Marshal will conduct a plan review and issue a project clearance letter or an operational permit.  PLEASE ALLOW UP TO 14 BUSINESS DAYS.

    Questions?  call (801)677.2400